Governor's Mansion Renovation All Records
|
Note ID: | MS708 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - First Floor - Stair Hall (E/R) | Work Type: | Miscellaneous | Notes: | New chairrail and baseboard have been installed in the North and South Stairhalls. Wiring has been brought to the wall surface in anticipation of switchplate installation. |
|
|
Note ID: | MS722 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - First Floor - Stair Hall (E/R) | Work Type: | Demolition | Notes: | The brick wall near the south stair to the basement is "notched" to accommodate the numerous switches scheduled to be placed in this corner. |
|
|
Note ID: | MS701 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - North Elevation | Work Type: | New Finish Application | Notes: | Scaffolding remains up on the south, north, and west sides of the Mansion while painting continues. The rooftop balustrade has been restored and extra balusters are stored in the attic. |
No image available
|
|
Note ID: | MS713 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Above Ballrooms | Work Type: | New Finish Application | Notes: | Remilled, quarter-sawn, heart pine flooring has been installed in the new Family Room and other spaces over the North and South Ballrooms. |
|
|
Note ID: | MS718 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Bedroom and Bathroom #2 (R) | Work Type: | New Finish Application | Notes: | A new tile shower wall and floor have been installed in Bathroom #2. |
|
|
Note ID: | MS719 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Bedroom and Bathroom #2 (R) | Work Type: | New Finish Application | Notes: | The walls of Bedroom #2 have been spackled in preparation for the finish coats of paint. Remilled, quarter-sawn, heart pine flooring has been installed |
|
|
Note ID: | MS721 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Capitol Room (E/R) | Work Type: | Miscellaneous | Notes: | Minor repairs to window sash are completed in the 2nd Floor to ensure smooth operation. The Capitol Room is used to lay out some repair jobs. |
|
|
Note ID: | MS720 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Dressing Room and Bedroom (E) / Governor's Bedroom (R) | Work Type: | New Finish Application | Notes: | Remilled, quarter-sawn, heart pine flooring has been installed in the Governor's Bedroom. Wiring has been brought to the wall and ceiling surface in preparation for fixture, outlet, and switchplate installation. |
|
|
Note ID: | MS711 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Lafayette Room (E/R) | Work Type: | New Finish Application | Notes: | Plaster repairs continue in preparation for installation of finishes in the Lafayette Bedroom. Sheetrock has been laminated to the ceiling. |
|
|
Note ID: | MS717 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Library (E/R) | Work Type: | Miscellaneous | Notes: | The north wall of the Library has not yet been repaired. |
|