Governor's Mansion Renovation All Records
|
Note ID: | MS714 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | New Finish Application | Notes: | New baseboard, chairrail, and door casings have been installed in the new Family Room. Walls and ceiling have been resurfaced with gypsum drywall. |
|
|
Note ID: | MS712 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Old Governor's Bedroom (E/R) | Work Type: | New Finish Application | Notes: | Plaster repairs continue in preparation for installation of finishes in the Old Governor's Bedroom. Sheetrock has been laminated to the ceiling. |
|
|
Note ID: | MS716 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - Second Floor - Private Dining Room, Bathroom, and Powder Room (E) / Bedroom and Bathroom #3 (R) | Work Type: | New Finish Application | Notes: | New baseboard, chairrail, and door casings have been installed in the Bedroom #3. Walls and ceiling have been resurfaced with gypsum drywall. As with all rooms above the North and South Ballrooms, remilled, quarter-sawn, heart pine flooring has been installed. The walls have been spackled in preparation for the finish coats of paint. |
|
|
Note ID: | MS723 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - South Elevation | Work Type: | Miscellaneous | Notes: | Painting the South elevation nears completion. The roof balustrade has been repaired. The chimneys have not yet been repainted. |
|
|
Note ID: | MS700 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - South Elevation | Work Type: | New Finish Application | Notes: | Scaffolding remains up on the south, north, and west sides of the Mansion while painting continues. The rooftop balustrade has been restored and extra balusters are stored in the attic. |
|
|
Note ID: | MS702 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Mansion - West Elevation | Work Type: | New Finish Application | Notes: | Scaffolding remains up on the south, north, and west sides of the Mansion while painting continues. The rooftop balustrade has been restored and extra balusters are stored in the attic. |
No image available
|
|
Note ID: | MS695 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Site - General | Work Type: | New Concrete Construction | Notes: | A new driveway and retaining wall have been poured on the north and east sides of the project site. Because of the changed grade, new steps will connect the North Garden to the driveway. |
|
|
Note ID: | MS699 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Site - South Garden | Work Type: | Miscellaneous | Notes: | Restored iron railings have been reinstalled on the stairs leading to the South Garden along the garden's west wall. |
|
|
Note ID: | MS694 | Weather Conditions: | Sunny, high 70s | Report Author: | Mary Harding Sadler | Report Date: | 10/2/1999 | Location: | Site - West Garden | Work Type: | Miscellaneous | Notes: | The new Guard House has been framed and sheathed in preparation for construction of the brick veneer. |
|
|
Note ID: | MS728 | Weather Conditions: | Scattered clouds, mid-70s. | Report Author: | Mary Harding Sadler | Report Date: | 10/4/1999 | Location: | Mansion - Basement - Hall (E) / Stairhall (R) | Work Type: | Framing | Notes: | Repairs and an extension to the north basement stair continue. Evidence of the earlier stringer remains on the stair's east wall. |
|