Governor's Mansion Renovation All Records
|
Note ID: | MS793 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - Old Governor's Office (E/R) | Work Type: | New Finish Application | Notes: | Painters have begun priming the wood trim in the Old Governor's Office. An ornamental brass and iron coal grate has been delivered for the fireplace. |
No image available
|
|
Note ID: | MS797 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - Restroom (A) | Work Type: | Miscellaneous | Notes: | New casework supporting the Powder Room's lavatories has been installed. This casework has a number of carefullly executed details, such as chamfering. |
No image available
|
|
Note ID: | MS794 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - South Ballroom (E/R) | Work Type: | New Finish Application | Notes: | Painting is complete in the South Ballroom except for the marbelizing. The wall paper border has been installed. The cleaned and slightly reconfigured chandelier has been installed by Bill Toombs' group. The chandelier is temporarily protected by plastic. |
No image available
|
|
Note ID: | MS799 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - South Ballroom (E/R) | Work Type: | Miscellaneous | Notes: | The new linear diffuser is relatively unobtrusive in its position behind the deep beam separating the Ballroom from the center hall. |
No image available
|
|
Note ID: | MS792 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - South Foyer (E/R) | Work Type: | New Finish Application | Notes: | The new parquet flooring has been installed in the South Foyer. |
No image available
|
|
Note ID: | MS800 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - First Floor - Stair Hall (E/R) | Work Type: | New Finish Application | Notes: | Painter applies a prime coat of paint to the very tall walls of the Stairhall as plaster repairs are completed below. |
No image available
|
|
Note ID: | MS785 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - North Elevation | Work Type: | Miscellaneous | Notes: | Repairs to the North Portico continue. Both caps and bases of the pilasters and columns have been repaired with new elements. |
No image available
|
|
Note ID: | MS802 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - Second Floor - Bath #4 (E/R) | Work Type: | Miscellaneous | Notes: | The window in Bathroom #4 has not yet received its new sill. |
No image available
|
|
Note ID: | MS801 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - Second Floor - Lafayette Room (E/R) | Work Type: | New Finish Application | Notes: | The wood trim, walls, and newly restored mantel have been primed in the Lafayette Bedroom. |
No image available
|
|
Note ID: | MS803 | Weather Conditions: | Sunny, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 10/31/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | Miscellaneous | Notes: | Finish carpenters continue to install new trim and casing throughout the Mansion. |
No image available
|