Pages :   1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125   Previous  Next Page

Note ID: MS791
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Mansion - South Elevation
Work Type: Miscellaneous
Notes: Painting the South elevation is almost complete. The new South Portico lantern made by Bill Toombs to convey the same character, at a smaller scale, as the lantern on the West Portico, has been installed. The stripped and repaired balustrade has been reinstalled on the porch, but it has not yet been repainted.


No image available


Note ID: MS787
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Mansion - West Elevation
Work Type: Miscellaneous
Notes: Restoration of the West (front) Portico is nearly complete. New cast fleurettes and other ornament have been fabricated and installed to match the historic moldings. The lantern restored by Bill Toombs has been reinstalled.


Governor's Mansion Renovation Photograph  


Note ID: MS786
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Site - General
Work Type: Miscellaneous
Notes: New landscaping materials have been planted along the bank that rises from Governor's Street into Capitol Square and the Governor's Mansion precinct.


No image available


Note ID: MS789
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Site - General
Work Type: Miscellaneous
Notes: Paving of the newly reconfigured driveway continues.


No image available


Note ID: MS790
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Site - South Garden
Work Type: Miscellaneous
Notes: A massive clean-up effort is underway, inside and out, as the project draws to a close.


No image available


Note ID: MS784
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Site - West Garden
Work Type: Miscellaneous
Notes: A massive site clean-up effort is underway, combined with efforts to plant new landscape materials. New sod has been mounded around the fountain in the center of the entry court. The paved driveway is rinsed with water and scoured with brushes rotating beneath a small street-cleaning vehicle.


Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  


Note ID: MS783
Weather Conditions: Sunny, mid-70s
Report Author: Mary Harding Sadler
Report Date: 10/31/1999
Location: Site - West Garden
Work Type: New Masonry Construction
Notes: The brick veneer on the new Guard House has been installed, along with cast stone sills and framing for the new windows.


Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  


Note ID: JL466
Weather Conditions: Rainy, mid 70's
Report Author: Joseph D. Lahendro
Report Date: 11/2/1999
Location: Mansion - First Floor - Dining Room (E/R)
Work Type: Floor Conservation
Notes: Video and digital photos of floor refinishing test patch, descibed above, following drying.


Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  


Note ID: JL470
Weather Conditions: Rainy, mid 70's
Report Author: Joseph D. Lahendro
Report Date: 11/2/1999
Location: Mansion - First Floor - Ladies Parlor (E/R)
Work Type: New Finish Application
Notes: Video and digital photos of paperhanger installing wallpaper liner over plaster walls. Liner is fiberglass material, and is made to go underneath wallpaper. Liner must be primed with paint before installing wallpaper.


No image available


Note ID: JL465
Weather Conditions: Rainy, mid 70's
Report Author: Joseph D. Lahendro
Report Date: 11/2/1999
Location: Mansion - First Floor - Stair Hall (E/R)
Work Type: New Finish Application
Notes: Video and digital photos of plasterers working on north stair walls, sanding new plaster skim coat applied over previously painted plaster walls because architect decided existing walls were too rough. Views of completed skimed walls in south stair.


Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  Governor's Mansion Renovation Photograph  
Governor's Mansion Renovation Photograph  

Pages :   1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125   Previous  Next Page

facebook twitter youtube instagram linkedin