Note ID: | MS831 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Mansion - Second Floor - Library (E/R) | Work Type: | New Finish Application | Notes: | The north wall of the Library has been finished with new grass paper. The paneled wainscot has been reinstalled. |
No image available
|
|
Note ID: | MS827 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | New Finish Application | Notes: | The new Family Room appears to be completely finished except for installion of switch and outlet plates. |
No image available
|
|
Note ID: | MS823 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Mansion - Second Floor - Private Dining Room, Bathroom, and Powder Room (E) / Bedroom and Bathroom #3 (R) | Work Type: | New Finish Application | Notes: | Bedroom #3 appears to be completely finished. |
No image available
|
|
Note ID: | MS818 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Mansion - South Elevation | Work Type: | New Finish Application | Notes: | The task of painting the Mansion's south elevation and its trim appears to be complete, including the chimneys, the roof balustrade, the garden wall, the portico, and trim. |
No image available
|
|
Note ID: | MS809 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Site - General | Work Type: | Miscellaneous | Notes: | Work continues on the brick paved garden walk outside of the east wall of the South Garden. More landscap materials have been planted along its edges. |
No image available
|
|
Note ID: | MS807 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Site - General | Work Type: | Miscellaneous | Notes: | New brick garden steps and a brick clad retaining wall have been completed along the driveway serving the north side of the Mansion. |
No image available
|
|
Note ID: | MS810 | Weather Conditions: | Sunny, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 11/13/1999 | Location: | Site - South Garden | Work Type: | Miscellaneous | Notes: | Two new footings are bridged with a cast concrete beam so that the reconfigured garden wall at the southeast corner of the South Garden will not damage an old tree. |
No image available
|
|
Note ID: | JL491 | Weather Conditions: | Sunny, low 50's | Report Author: | Joseph D. Lahendro | Report Date: | 11/18/1999 | Location: | Mansion - Basement - General | Work Type: | Miscellaneous | Notes: | Video and digital photos of completed basement kitchen areas showing progress of moving in furniture and foodstuffs. Chief giving tour of new kitchen. New carpet on north and south stairs. |
|
|
Note ID: | JL490 | Weather Conditions: | Sunny, low 50's | Report Author: | Joseph D. Lahendro | Report Date: | 11/18/1999 | Location: | Mansion - East Elevation | Work Type: | New Masonry Construction | Notes: | Video and digital photos of newly installed brick paving on curving sidewalk east of house. |
|
|
Note ID: | JL498 | Weather Conditions: | Sunny, low 50's | Report Author: | Joseph D. Lahendro | Report Date: | 11/18/1999 | Location: | Mansion - First Floor - Dining Room (E/R) | Work Type: | Floor Conservation | Notes: | Video and digital photos of completed oak flooring refinishing. |
|