Governor's Mansion Renovation All Records
|
Note ID: | MS309 | Weather Conditions: | Scattered clouds, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 6/19/1999 | Location: | Mansion - Second Floor - Dressing Room and Bedroom (E) / Governor's Bedroom (R) | Work Type: | Demolition | Notes: | Demolition of the brick wall joining the original Mansion to the Governor's Bedroom has begun and will be completed within the day. The work is done very painstakingly because the wall is in close proximity to elements which must be preserved. The adjacent ceiling of the former Governor's Bedroom is temporarily shored up. |
|
|
Note ID: | MS314 | Weather Conditions: | Scattered clouds, mid-70s | Report Author: | Mary Harding Sadler | Report Date: | 6/19/1999 | Location: | Mansion - Second Floor - Dressing Room and Bedroom (E) / Governor's Bedroom (R) | Work Type: | Demolition | Notes: | The demolition of the 2nd floor brick wall in the former Governor's Bedroom is hardly noticeable from Governor's Street, on the Mansion's north side. |
|
|
Note ID: | MS319 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Attic | Work Type: | Miscellaneous | Notes: | Mechanical equipment and ductwork fills the attic perimeter. |
|
|
Note ID: | MS322 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Entrance Hall (A) | Work Type: | New Concrete Construction | Notes: | The formwork has been removed from the new elevator pit. |
|
|
Note ID: | MS321 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Hall (E) / Hall and Dumbwaiter (R) | Work Type: | Miscellaneous | Notes: | The new dumbwaiter has been set in place and the concrete block walls of its shaft are under construction. |
|
|
Note ID: | MS325 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Hall (E) / Stairhall (R) | Work Type: | Framing | Notes: | At the center of the Stairhall's long axis, a newly framed opening will lead to the Service Hall. |
|
|
Note ID: | MS320 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Mansion Director (E/R) | Work Type: | Miscellaneous | Notes: | Utilities infrastructure continues to be added in the joist cavities of the Mansion Director's Office. The rooms and Stairhall comprising the north-south "axis" of spaces along the west side of the mansion, incorporate a critical path for utilities. |
|
|
Note ID: | MS324 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Security Office (E) / Executive Protection Unit (R) | Work Type: | Miscellaneous | Notes: | Utilities infrastructure continues to be added to the Security Office. Like the adjacent Stairhall, the axis connecting the Security Area to the Mansion Director's Office, is a critical path for utilities. The heavy timber headers removed from over the window openings lie on the floor before being taken to the dump. |
|
|
Note ID: | MS323 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - Basement - Women (R) | Work Type: | Miscellaneous | Notes: | Mechanical and other utilities are being installed in the new Women's Room. |
|
|
Note ID: | MS315 | Weather Conditions: | Mostly cloudy, mid-60s | Report Author: | Mary Harding Sadler | Report Date: | 6/21/1999 | Location: | Mansion - First Floor - Old Governor's Office (E/R) | Work Type: | New Finish Application | Notes: | The doors uncovered in the Old Governor's Office will be removed and taken off site. They will be grained and refinished like the other doors on the 1st Floor. |
|