Note ID: | MS386 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Carriage House - Upper Floor (east to west) - Room 11 | Work Type: | Framing | Notes: | Walls and ceilings are being framed and utilities roughed in. |
|
|
Note ID: | MS384 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Carriage House - Upper Floor (east to west) - Room 7 | Work Type: | Miscellaneous | Notes: | Framing and utilities rough-in at the Carriage House appears to be nearly complete. |
|
|
Note ID: | MS385 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Carriage House - Upper Floor (east to west) - Room 9 | Work Type: | New Finish Application | Notes: | Framing and rough-in are complete. Contractors have begun to surface the new walls with drywall. |
|
|
Note ID: | MS395 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Cottage - East Elevation | Work Type: | Excavation | Notes: | The area in front of the Cottage is being excavated for utilities installtion. An old brick utility line is discovered in the process. |
|
|
Note ID: | MS392 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Cottage - Second Floor - South Bedroom (E/R) | Work Type: | New Finish Application | Notes: | Temporary carpet is being laid in the Cottage's 2nd floor south bedroom. The space will be used for project meetings. |
|
|
Note ID: | MS398 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Mansion - First Floor - Dining Room (E/R) | Work Type: | Miscellaneous | Notes: | The mechanical unit that will temper air supplied to the South Ballroom has arrived and is temporarily stored in the Dining Room before it is mounted in the ceiling of the Scullery. |
|
|
Note ID: | MS400 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Mansion - First Floor - Entrance Hall (E/R) | Work Type: | Miscellaneous | Notes: | The brick wall adjacent to the main entry is channeled in order to recess electrical wiring. |
|
|
Note ID: | MS399 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Mansion - First Floor - Scullery (E/R) | Work Type: | Miscellaneous | Notes: | Preparations are completed for mounting the mechanical unit in the ceiling of the Scullery. This unit will supply tempered air to the South Ballroom. This is the same approach that will be used in the North Ballroom. |
|
|
Note ID: | MS396 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Mansion - Second Floor - Above Ballrooms | Work Type: | Framing | Notes: | The process of leveling the 2nd floor over the North and South Ballrooms continues. Demolition of wall finishes to the south of the chimney mass reveals the limit of the 2nd floor north chimney mass, as well as earlier wall finishes 12" behind the existing plaster plane. |
|
|
Note ID: | MS397 | Weather Conditions: | Partly cloudy, high 80s | Report Author: | Mary Harding Sadler | Report Date: | 7/7/1999 | Location: | Mansion - Second Floor - Dressing Room (E) / Governor's Dressing Room and Bathroom (R) | Work Type: | Miscellaneous | Notes: | the opening for an 18' long linear diffuser is cut into the floor joists for what will be the Governor's Dressing Room. The tops of the joists are cut, reducing the depth of the joists by 2/3's of their historic depth, to make room for the mechanical duct. The mechanical unit will be hung in the ceiling of the Scullery adjacent to the south end of the Dining Room. |
|