Governor's Mansion Renovation All Records
|
Note ID: | MS628 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - First Floor - Restroom (A) | Work Type: | Framing | Notes: | A window from the Dining Room will be retained in place but blocked up in order to enclose the new 1st Floor Powder Room. |
|
|
Note ID: | MS621 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - First Floor - South Ballroom (E/R) | Work Type: | New Finish Application | Notes: | Colonial Williamsburg staff making the curtains have brought muslin models to try in the actual window openings. |
|
|
Note ID: | MS645 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - North Elevation | Work Type: | On-site paint removal | Notes: | Workers continue the painstaking process of removing paint from the fluted columns of the North Portico. |
|
|
Note ID: | MS638 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Capitol Room (E/R) | Work Type: | Miscellaneous | Notes: | The finish carpenters are repairing a door that was damaged by termite infestation. A filler will restore integrity to the damaged rail, and the entire door will be refinished. No repair will be evident when the job is complete. |
|
|
Note ID: | MS643 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Dressing Room and Bedroom (E) / Governor's Bedroom (R) | Work Type: | Miscellaneous | Notes: | The finish carpenters are installing a two-piece chairrail throughout the private quarters of the the 2nd floor. |
|
|
Note ID: | MS642 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Library (E/R) | Work Type: | Miscellaneous | Notes: | A miter saw has been set up in the Library for the finish carpenters from Restoration Builders of Virginia to size and miter trim pieces. |
|
|
Note ID: | MS639 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | Miscellaneous | Notes: | New drywall is laminated to the east wall of the new Family Room, covering a mix of finishes remaining from the bathroom and closet that occupied the northeast corner of the 2nd Floor. The new doorway has been framed in. The electricians are wiring the space. |
|
|
Note ID: | MS644 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Old Governor's Bedroom (E/R) | Work Type: | Miscellaneous | Notes: | New finish trim is stored for the finish carpenters in the Old Governor's Bedroom. |
|
|
Note ID: | MS641 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - Second Floor - Private Dining Room, Bathroom, and Powder Room (E) / Bedroom and Bathroom #3 (R) | Work Type: | New Finish Application | Notes: | New door casing and trim are complete in Bedroom #3. Priming the drywall has not started in this area. |
|
|
Note ID: | MS617 | Weather Conditions: | partly cloudy, low 80s | Report Author: | Mary Harding Sadler | Report Date: | 9/7/1999 | Location: | Mansion - South Elevation | Work Type: | On-site paint removal | Notes: | Paint removal continues on the exterior. A temporary polyethylene curtain encloses the elevation and a polyethylene gutter lines the areaway so that toxic runoff from the cleaning process can be contained and controlled. |
|