Governor's Mansion Renovation All Records
|
Note ID: | MS655 | Weather Conditions: | Partly cloudy, low 70s | Report Author: | Mary Harding Sadler | Report Date: | 9/17/1999 | Location: | Mansion - Second Floor - Above Ballrooms | Work Type: | New Finish Application | Notes: | The rooms over the North and South Ballrooms have been trimmed with new baseboard, chairrail and a small crown molding. This treatment is typical throughout the First Family's private quarters. The new trim matches the historic trim found in the 2nd Floor front rooms. |
|
|
Note ID: | MS653 | Weather Conditions: | Partly cloudy, low 70s | Report Author: | Mary Harding Sadler | Report Date: | 9/17/1999 | Location: | Mansion - Second Floor - Capitol Room (E/R) | Work Type: | Miscellaneous | Notes: | The cased opening leading from the Capitol Room into the First Family's private quarters has been reduced in size and double-doors have been installed. The new doorway is slightly recessed within the original opening. |
|
|
Note ID: | MS650 | Weather Conditions: | Partly cloudy, low 70s | Report Author: | Mary Harding Sadler | Report Date: | 9/17/1999 | Location: | Mansion - Second Floor - Elevator Foyer (A) | Work Type: | Miscellaneous | Notes: | The new elevator shaft is complete and elevator equipment and machinery is being installed within the shaft and in the basement level Machine Room. |
|
|
Note ID: | MS654 | Weather Conditions: | Partly cloudy, low 70s | Report Author: | Mary Harding Sadler | Report Date: | 9/17/1999 | Location: | Mansion - Second Floor - Private Dining Room, Bathroom, and Powder Room (E) / Bedroom and Bathroom #3 (R) | Work Type: | New Finish Application | Notes: | The drywall is being painted with a green tinted primer in Bedroom #3. The room has been trimmed with new baseboard, chairrail and a small crown molding. The new trim matches the historic trim found in the 2nd Floor front rooms. |
|
|
Note ID: | MS665 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Carriage House - North Elevation | Work Type: | Window Conservation | Notes: | Historic windows are being repaired on site by the abatement contractor. Glazing putty and glazing have been removed so that the paint can be removed and window sash can be repaired and re-glazed. |
|
|
Note ID: | MS666 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Cottage - East Elevation | Work Type: | New Finish Application | Notes: | The exterior walls, trim, and railings of the Cottage are being painted. The entry doors have been stripped of paint and have been hung in place for repainting. A new brick patio has been installed at the ground level. |
|
|
Note ID: | MS693 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Cottage - West Elevation | Work Type: | New Finish Application | Notes: | Paint is being removed from the stone jack arches and window sills on the Cottage using "Peel Away." |
|
|
Note ID: | MS676 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Entrance Hall (A) | Work Type: | New Masonry Construction | Notes: | The former window opening from the north wall of the Scullery has been filled with salvaged brick laid with Portland cement mortar. The new doorway connecting this new Entrance Hall to the Restroom Hall has been framed in. |
|
|
Note ID: | MS679 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Hall (E) / Hall and Dumbwaiter (R) | Work Type: | Miscellaneous | Notes: | The tile work is complete around the dumbwaiter. The new appliances are inplace and are being hooked up. At the rear of the dumbwaiter new steps leading to the 2nd floor Scullery have been constructed. Drop-in lighting and ceiling tiles are being installed. |
|
|
Note ID: | MS680 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Hall (E) / Service Hall (R) | Work Type: | New Finish Application | Notes: | The walls, doors, and casings of the Service Hall have been primed. The drop-in lights and ceiling tiles are being installed. |
|