Governor's Mansion Renovation All Records
|
Note ID: | JL276 | Weather Conditions: | Sunny, Low 90's | Report Author: | Joseph D. Lahendro | Report Date: | 8/13/1999 | Location: | Mansion - Second Floor - Family Kitchen (A) | Work Type: | Demolition | Notes: | Video and digital photos of partial removal of wood eave (fascia, crown molding and modillion blocks) at the north outside wall of the early 20th century bedroom addition. |
|
|
Note ID: | JL275 | Weather Conditions: | Sunny, Low 90's | Report Author: | Joseph D. Lahendro | Report Date: | 8/13/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | Demolition | Notes: | Video and digital photos of east window following removal of window sash and frame. Steel lintel above indicates modern reworking of this window. But the splayed brick jambs and integral wood nailer blocks appear original. |
|
|
Note ID: | JL277 | Weather Conditions: | Sunny, Low 90's | Report Author: | Joseph D. Lahendro | Report Date: | 8/13/1999 | Location: | Mansion - South Elevation | Work Type: | Demolition | Notes: | Video and digital photos of west stair to elevated walkway, connecting mansion with cottage, following its removal. Evidence of stair brick walls not tied to walkway walls, and painted brick on walkway wall covered by stair, indicates the stair is not original to the walkway. New stone stair treads stored next to stair ready for installation on replacement stair. |
|
|
Note ID: | JL267 | Weather Conditions: | Sunny, Low 90's | Report Author: | Joseph D. Lahendro | Report Date: | 8/13/1999 | Location: | Mansion - West Elevation | Work Type: | Window Conservation | Notes: | Video and digital photos of removal of second floor window sash for off-site paint removal and repair. |
|
|
Note ID: | JL268 | Weather Conditions: | Sunny, Low 90's | Report Author: | Joseph D. Lahendro | Report Date: | 8/13/1999 | Location: | Mansion - West Elevation | Work Type: | On-site paint removal | Notes: | Video and digital photos of Peel-Away paint removal system applied to stone window sills and stone belt course. Views of stone belt course south of portico where Peel-Away has been removed; stone damage and prior patching evident. |
|
|
Note ID: | MS557 | Weather Conditions: | Hazy, low 90s | Report Author: | Mary Harding Sadler | Report Date: | 8/17/1999 | Location: | Mansion - Basement - Hall (E) / Service Hall (R) | Work Type: | New Finish Application | Notes: | Finishes and casing have been installed in the Service Hall. Wood storage units are stored in the hall awaiting installation. Drywall has been primed. |
|
|
Note ID: | MS556 | Weather Conditions: | Hazy, low 90s | Report Author: | Mary Harding Sadler | Report Date: | 8/17/1999 | Location: | Mansion - Basement - Kitchen (E/R) | Work Type: | New Finish Application | Notes: | Tile men from Satterwhite are installing wall tile in the Kitchen. Brick-shaped terra cotta floor tile have already been installed and are protected with a temporary cover. |
|
|
Note ID: | MS559 | Weather Conditions: | Hazy, low 90s | Report Author: | Mary Harding Sadler | Report Date: | 8/17/1999 | Location: | Mansion - Basement - Mansion Director (E/R) | Work Type: | New Finish Application | Notes: | The Mansion Director's Office is being trimmed out with new baseboards. Batt insulation installed between the joists will deaden sound. |
|
|
Note ID: | MS558 | Weather Conditions: | Hazy, low 90s | Report Author: | Mary Harding Sadler | Report Date: | 8/17/1999 | Location: | Mansion - Basement - Men (R) | Work Type: | New Finish Application | Notes: | Water resistant drywall has been installed in the Men's Room. It is taped and mudded. Tile men from Satterwhite have begun to install the white marble floor tile using a thin set approach. |
|
|
Note ID: | MS544 | Weather Conditions: | Hazy, low 90s | Report Author: | Mary Harding Sadler | Report Date: | 8/17/1999 | Location: | Mansion - East Elevation | Work Type: | New Masonry Construction | Notes: | New brick veneer is being added to the north and east elevations of the new addition. Installation of the brick veneer is now above the 2nd floor level. New, tooled, limestone trim has been installed to match the historic trim. |
|