Governor's Mansion Renovation All Records
|
Note ID: | MS596 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Attic | Work Type: | New Finish Application | Notes: | Installation of new drywall has begun in the attic. Wiring has been roughed in, along with other utilities. |
|
|
Note ID: | MS580 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Dry Storage (A) | Work Type: | Miscellaneous | Notes: | The space assigned to be Dry Storage adjacent to the Kitchen in the new addition has become the "guts" of the new wet and dry sprinkler system. |
No image available
|
|
Note ID: | MS579 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Dry Storage (A) | Work Type: | Framing | Notes: | Interior framing of the new addition is nearly complete. |
|
|
Note ID: | MS581 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Kitchen (E/R) | Work Type: | Miscellaneous | Notes: | Wall tile installation is complete in the kitchen and final utilities installation is underway. At the south end of the kitchen, gypsum wallboard ceiling installation has begun. New kitchen appliances and equipment arrive, such as the enormous hood. Some equipment is already mounted in place. |
|
|
Note ID: | MS597 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Men (R) | Work Type: | New Finish Application | Notes: | White marble is applied to walls and floor in the Men's Room by Satterwhite's stone tile specialists. |
|
|
Note ID: | MS584 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Restroom Hall (R) | Work Type: | Miscellaneous | Notes: | The elevator equipment is being installed at the end of the Restroom Corridor. Door casings along the corridor have been installed by the finish carpenters. |
|
|
Note ID: | MS583 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Security Office (E) / Executive Protection Unit (R) | Work Type: | Miscellaneous | Notes: | The new HVAC system is tested using a computer program run on a notebook computer taken from room to room. The framing for the new suspended acoustical ceiling has been installed but neither lighting nor acoustical panels have been installed (those boxed fixtures are stacked in the room). |
|
|
Note ID: | MS582 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - Basement - Women (R) | Work Type: | New Finish Application | Notes: | White marble tiles are installed on floor and walls of the Women's Room in a "thin-set" application. |
|
|
Note ID: | MS576 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - East Elevation | Work Type: | Excavation | Notes: | Trenching on the east side of the Mansion has resumed. No artifacts are seen or reported. A number of utililty lines, including a 6" sanitary line, lead from the kitchen to a new utility yard adjacent to the kitchen and beyond. |
|
|
Note ID: | MS590 | Weather Conditions: | Partly cloudy, mid-80s | Report Author: | Mary Harding Sadler | Report Date: | 8/24/1999 | Location: | Mansion - First Floor - Dining Room (E/R) | Work Type: | Miscellaneous | Notes: | New wiring is being roughed in the Dining Room. Antique sconces supplement the Dining Room chandelier (these fixtures are being cleaned, repaired, and, in some cases, subtly refined by lighting specialist Bill Toombs). |
|