Note ID: | MS615 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Above Ballrooms | Work Type: | New Finish Application | Notes: | New drywall has been installed, taped, and mudded in the 2nd floor area above the Ballrooms. A long corridor connects the Family Room (on the north) to the bedrooms on the south. |
|
|
Note ID: | MS610 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Bath #4 (E/R) | Work Type: | Miscellaneous | Notes: | The channel cut in the brick wall adjacent to the Bathroom #4 window has been filled with ready-mix concrete. |
|
|
Note ID: | MS612 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Dressing Room and Bedroom (E) / Governor's Bedroom (R) | Work Type: | New Finish Application | Notes: | New trim is being installed and primed in the hallway leading to the new Governor's Bedroom. Drywall has been installed, taped, and mudded at walls and ceilings. |
|
|
Note ID: | MS606 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Elevator Foyer (A) | Work Type: | Miscellaneous | Notes: | Workmen are installing the elevator machinery within the new shaft. |
|
|
Note ID: | MS609 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Lafayette Room (E/R) | Work Type: | Miscellaneous | Notes: | The channel cut in the brick wall adjacent to the Lafayette Bedroom door has been filled with ready-mix concrete. |
|
|
Note ID: | MS611 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | Demolition | Notes: | The new door opening has been created between the new Family Room and the new Elevator Foyer by lengthening the existing original window opening. |
|
|
Note ID: | MS604 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Northeast Bedroom and Bath (E) / Family Room (R) | Work Type: | Demolition | Notes: | The window opening has been enlarged to create a door from the new Family Room into the Elevator Foyer. Some Family Room walls have been sheathed with gypsum drywall in preparation for new trim and finishes. |
|
|
Note ID: | MS608 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Old Governor's Bedroom (E/R) | Work Type: | Miscellaneous | Notes: | The channel cut in the brick wall adjacent to the Old Governor's Bedroom door has been filled with ready-mix concrete. |
|
|
Note ID: | MS607 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Old Governor's Bedroom (E/R) | Work Type: | Miscellaneous | Notes: | New 6-panel doors have been primed and brought on site for installation on the 2nd floor. They are being temporarily stored in the Old Governor's Bedroom. |
No image available
|
|
Note ID: | MS613 | Weather Conditions: | | Report Author: | Mary Harding Sadler | Report Date: | 9/3/1999 | Location: | Mansion - Second Floor - Private Dining Room, Bathroom, and Powder Room (E) / Bedroom and Bathroom #3 (R) | Work Type: | New Finish Application | Notes: | New trim is being installed and primed in Bedroom #3. Drywall has been installed, taped, and mudded at walls and ceilings. |
|