Governor's Mansion Renovation All Records
|
Note ID: | MS677 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Kitchen (E/R) | Work Type: | Miscellaneous | Notes: | Much of the new Kitchen equipment and appliances has been moved into place and hooked up. New lighting fixtures have been installed, as have the new walk-in refrigerator and freezer. |
|
|
Note ID: | MS681 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Mansion Director (E/R) | Work Type: | New Finish Application | Notes: | The walls, trim, and casings have been primed in the Mansion Director's Office. The drop-in lights and ceiling tiles are being installed. |
|
|
Note ID: | MS678 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Pantry (E) / Office (R) | Work Type: | Framing | Notes: | The walls and doorway of the Chef's Office have been furred out with steel studs. |
|
|
Note ID: | MS682 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - Basement - Security Office (E) / Executive Protection Unit (R) | Work Type: | New Finish Application | Notes: | The walls and casings have been primed in the Security Office. The drop-in lights and ceiling tiles are being installed. Slate wills have been set in the windows. |
|
|
Note ID: | MS663 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - East Elevation | Work Type: | On-site paint removal | Notes: | Paint removal continues on the east elevation. Some removal is complete, in the section of wall adjacent to the new addition. Here a prime coat has been sprayed on the brick. Windows have been masked to prevent damage during the paint removal process, and to prevent sprayed paint from building up on the window glazing. |
|
|
Note ID: | MS673 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - First Floor - Breakfast Room (E/R) | Work Type: | Miscellaneous | Notes: | Finish carpenter Arthur Woodward solves the puzzle of reusing the threshold and hinge in the modified doorway connecting the Breakfast Room to the Scullery. |
|
|
Note ID: | MS672 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - First Floor - Dining Room (E/R) | Work Type: | New Finish Application | Notes: | Plaster repairs have begun in the Dining Room. Cracks are being cleaned out and filled. The window sash in the north end wall of the Dining Room will be filled with mirrors. On the other side of the window is a new Powder Room. |
|
|
Note ID: | MS675 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - First Floor - Entrance Hall (E/R) | Work Type: | New Finish Application | Notes: | The walls of the Entry Hall have been primed a soft gray color. The wood trim has not yet received a new coat of paint. |
|
|
Note ID: | MS669 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - First Floor - Entrance Hall (E/R) | Work Type: | New Finish Application | Notes: | A variety of finish colors are being tested in the front rooms of the 1st Floor. |
|
|
Note ID: | MS670 | Weather Conditions: | Partly cloudy, low 60s | Report Author: | Mary Harding Sadler | Report Date: | 9/22/1999 | Location: | Mansion - First Floor - Old Governor's Office (E/R) | Work Type: | New Finish Application | Notes: | A variety of finish colors are being tested in the front rooms of the 1st Floor. |
|