Governor's Mansion Renovation All Records
|
Note ID: | JL330 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - First Floor - North Ballroom (E/R) | Work Type: | Demolition | Notes: | Video and digital photos of northernmost window on east wall where the sash, bottom frame and brick panel below window have been removed to create a new door to the new northeast addition. Window frame and woodwork appear to be early 20th century. Brick wall removed is original rear, east wall of mansion. Close-up views of broken brick wall ends. |
|
|
Note ID: | JL343 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - First Floor - Old Governor's Office (E/R) | Work Type: | New Finish Application | Notes: | Video and digital photos of new overdoor moldings, at the two east doors, installed to replace moldings damaged when covered with a later wall to hide these doors, and which now has been removed. |
No image available
|
|
Note ID: | JL345 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - First Floor - Scullery (E/R) | Work Type: | New Finish Application | Notes: | Video and digital photos of workman installing waterproofing sheets at floor corners with walls. Waterproofing will be installed over entire floor before installation of quarry tile flooring. |
No image available
|
|
Note ID: | JL327 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - North Elevation | Work Type: | On-site paint removal | Notes: | Video and digital photos of paint removal progress from brick façade, which has just been completed. Workmen removing paint from door frame. |
|
|
Note ID: | JL328 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - North Elevation | Work Type: | Demolition | Notes: | Video and digital photos of access drive and landscape removal. |
|
|
Note ID: | JL340 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - North Elevation | Work Type: | New Masonry Construction | Notes: | Video and digital photos of workers installing new stair between driveway and gate to north enclosed garden. New stair is part of new retaining wall being built along south side of new driveway that connects with new northeast addition basement level. Existing soil being excavated for retaining wall matches the mixed clay and large river rock mixture found elsewhere on the site, and is believed to be historic fill material. |
|
|
Note ID: | JL342 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - North Elevation | Work Type: | On-site paint removal | Notes: | Video and digital photos of north portico following paint removal and before new paint priming. Northeast corner column has been removed, along with pilaster capital and base, for repair or replacement. Some new repairs have been made to the door frame. Wood matchstick paneling at the ceiling is obviously of the Victorian period and not original. Dutchmen in pilasters and columns indicate where former handrails were connected. Semi-circular fan light at north door was constructed as a unit separate from the door frame, which may be corroboration for theory that fan light is later than the door because originally the interior north stair landing butted against the inside of the door, not allowing for the fan light. |
|
|
Note ID: | JL341 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - North Elevation | Work Type: | On-site paint removal | Notes: | Video and digital photos of north façade showing removal of loose paint from brick wall and paint priming just beginning. |
|
|
Note ID: | JL348 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - Second Floor - Bath #1 (E/R) | Work Type: | Framing | Notes: | Video and digital photos of workmen installing metal framing for new shower walls and lowered ceiling. |
No image available
|
|
Note ID: | JL349 | Weather Conditions: | Sunny low 80s | Report Author: | Joseph D. Lahendro | Report Date: | 9/25/1999 | Location: | Mansion - Second Floor - Bath #4 (E/R) | Work Type: | New Finish Application | Notes: | Video and digital photos of workman sponge cleaning newly installed ceramic tile flooring. Corner waterproofing sheets apparent at bottom of walls. |
No image available
|